EAST RENOVATION | |||||
To better serve our Members and Community, our 1st floor (Downstairs) Desk has been expanded and improvements have been made. |
|||||
6/17/11Grand Celebration! | |||||
Mr. Jack Lussier cuts the ribbon | New seating | ||||
East Y Members & Staff | |||||
.................................................................................................................... | |||||
6/15/11Almost Done | |||||
.................................................................................................................... | |||||
6/3/11 Beautiful New Floors | |||||
As we move into the homestretch, you will notice the framing of the new construction taking place, complete |
|||||
.................................................................................................................... | |||||
5/18/11 Steady Progress | |||||
When you come into the branch you will notice that the new entrance doors to the gym are all framed out Matt Merrill |
|||||
.................................................................................................................... | |||||
5/10/11 Starting to take shape! | |||||
Future new opening to the gym | Where the new service desk will be | ||||
The expanded hole in the wall will be replaced by a bright new desk, and past the plywood is the new opening |
|||||
.................................................................................................................... | |||||
5/6/11 The Walls Come Tumbling Down! | |||||
New gym door in progress | Wall is down | ||||
One week of renovation is already down, along with many of the walls that were to be impacted by the plans! A lot of great progress has been made in the first days of the reconstruction. Please pardon a little extra noise as the project continues, and the new vision takes shape. Thanks, have a great weekend everyone! - Matt Merrill Interim East Branch Associate Executive Director |
|||||
.................................................................................................................... | |||||
5/3/11 Where the desk once stood... | |||||
Renovation is already well underway at the East YMCA! The space where our old front desk once stood has een cleared and temporary walls are up in preparation for our new, improved and expanded space. We are ery excited about the improved aethetics and customer service this change will provide for our community! o that end, we have also started replacing the clothing hooks from the Lifestyle Center hallway, and our free kit lockers are now located in the Lifestyle Center. This change should benefit our members in terms of onvenience and security. Thanks for your patience and support as we move forward on this journey. Thanks, Matt Merrill Interim East Branch Associate Executive Director |
|||||
.................................................................................................................... | |||||
5/2/11 The renovation has begun!
A reminder that during the renovation, the entrance is in the back of the building. Second floor access Thanks, Matt Merrill |
|||||
..................................................................................................................... | |||||
4/25/11 Excited to begin |
|||||
Hello everyone, We are very excited to begin construction on the expansion of our East YMCA Service Desk! Construction will start fist thing in the morning Monday May 2nd. We are asking all of our members and staff o enter at the back entrance of our building. You will see signs posted in our parking lot directing you towards he back entrance. Please check back frequently for updates. Thanks so much! Paul VanderVelde Branch Executive Director |
|||||